Status Update
S‡mi Network Connectivity Project
25 February, 2004
Update 1.1
á June: Base Open Net Hotspot(s) in Jokkmokk
http://csd.ssvl.kth.se/~csd2004-team18/pdisc.html
á August: At least 2 Remote Hotspots
á October: Connection by point to point relay of anchor hotspot in
o Jokkmokk
o Remote hotspots in the summer lands
á October: Simple SMTP Relay. Use of off the shelf computers, laptops and wifi.
á December: SMTP - Bundle ALG
o No relay routing
á Done - Simulation of Prophet algorithm
á June - Prophet routing protocol - draft
á June - Leggo simulation of prophet algorithm (MA project)
http://www.ludd.luth.se/~krossarn/smd147/
á November - Prophet routing protocol prototype
á December - Prophet Protocol Lab Tests
á April: First mock-up. The intention is here to demonstrate the kind of results produced by the network planning tool.
á September: First prototype, using not unrealistic assumptions.
á December: Second prototype, where important models have been improved.
September: Study initiated
September: Document the requirements for SNC relays and gateway. The analysis should include power, configuration, ruggedizing. Analysis should also include details of wifi utilization, including range, and the ability to realistically increase range though shaping and power within SNC constraints.
December: Design construction requirements and budget for equipment for the second year based on SeptemberÕs analysis
September: Produce initial Tiki containing SNC documentation, training material, downloads etc.
June: Training in Hotspot setup
á Field test of Prophet (routing) relays in summer lands (mesh routing of bundles)
o Specialized hardware to be used in test installations
o Initial test of relay installation Ð
¤ multiple remote hotspots
¤ fixed relays
¤ mobile relays
o Mapping and Location of Fixed Gateways using topographical tool
á Develop and Deploy WEB Caching
á Develop ALGs for Bundle to Apps (Apps yet to be determined, e.g FTP)
á Minor modifications to topographical network planning tool, due to change requests.
á Continue Training
á Continue Documenting
á System Deployment in designated area
á Field Test
á Minor modifications to topographical network planning tool, due to change requests.
á Continued App development
á Continued training
á Continue Documenting
o Including documentation to allow for continued spread of the system